Prepaid Energy Meter by using Arduino and GSM

The main idea of the project is to modernize our metering system using Arduino and GSM. Now-a-days technology has developed to a large extend. At the same time the necessity for systems with automation and high security are preferre

2025-06-28 16:34:35 - Adil Khan

Project Title

Prepaid Energy Meter by using Arduino and GSM

Project Area of Specialization Internet of ThingsProject Summary

The main idea of the project is tomodernize our metering system using Arduino and GSM. Now-a-days technology has developed to a large extend. At the same time the necessity for systems with automation and high security are preferred. So, by using one of the superlative technologies available we are designing a prepaid electricity meter using Arduino and GSM for commercial and domestic purposes. Old-style meter reading for electricity consumption and billing is done by human operator from houses to houses and building to building. This requires huge number of labour workers and long working hour to achieve complete area reading and billing. Human operator billing are suffer to reading errors as sometime in houses the electricity power meter is placed in place where it is not easily accessible. Labour billing work is sometime also restricted and is slowed down by bad climate conditions. By using this system we can avoid such kind of problems. This system also able to save the transformer from disposing. When current increase from the define threshold value the system trip the home load. 

Project Objectives

To convert regular WAPDA metering system in to prepaid energy meter.

To develop an automatic load tripping system in case of overloading.

To design a reliable secure energy metering system.

Project Implementation Method

1st step: first step include literature.

2nd step: component selection.

3rd step:pulse counting from meter through Arduino.

4th step: LCD, GSM, and IR sensor interfacing with Arduino.

5th step: Hardware implementation, and integration of hardware and software, 

6th: Testing and Result 

Benefits of the Project

Meter reader are not reliable.

Reduce electricity consuming when income is tight.

No billing errors.

No debt money.

No need of extra staff for meter reading.

Customer will be responsible for disconnections[3

Technical Details of Final Deliverable

No

starting week date

description of milestone

duration in weeks

1

13/09/018

literature review

       6

2

25/10/018

Initial circuit diagram

       4

3

22/11/018

Tasks simulation

       4

4

20/01/018

Arduino programming and design

       5

5

24/01/019

GSM module study

       3

6

14/02/019

Interfacing of GSM and ARDUINO

       4

7

14/03/019

Full project simulation

       3

8

4/04/019

Full project implementation

       4

No

1

2

3

4

5

6

7

8

Final Deliverable of the Project Hardware SystemType of Industry Energy Technologies Internet of Things (IoT)Sustainable Development Goals Affordable and Clean EnergyRequired Resources
Elapsed time in (days or weeks or month or quarter) since start of the project Milestone Deliverable
Month 1literature reviewstudy of related project article
Month 2initial circuit diagramcircutry
Month 3task simulationcircutry simulation
Month 4Arduino programming and Designcoding
Month 5Gsm module studypaper work
Month 6intefacing of gsm and arduinosimulation
Month 7full project simulationcircuit simulation
Month 8full project implementationimplementation of project in software
Month 9hardware implementationimplementation of hardware
Month 10test and resultchecking of outputs